Project Recap: Feltham Phases 3 & 4 Concluding Works

Project Recap: Feltham Phases 3 & 4 Concluding Works

19 September 2023

Enable Infrastructure proudly completed another significant milestone in collaboration with our client, Network Rail, on Feltham Phases 3 and 4. πŸ€πŸŒ†

πŸ—οΈ Monster Crane Marvel: We utilised impressive monster cranes to successfully install five signal gantries across various strategic locations.Β  The installation of signal gantries BEF2336, BEF2338, BEF2349, BEF2381, BEF2147, and BEF2207 marked significant milestones, expertly managed by our team in collaboration with Network Rail. These installations significantly contribute to the overall operational efficiency.🚦🏁

πŸ”Œ Cable Recovery: During the same period, our dedicated team successfully executed extensive cable recovery operations spanning multiple locations, totalling an impressive 6000 meters. Each connection restored was a step towards optimising the rail infrastructure. πŸ’‘πŸ”Œ

πŸš‚ Ensuring Clear Tracks: Minor route works were meticulously carried out, contributing to the overall safety and reliability of the tracks. This meticulous attention to detail ensured that the rail lines were in impeccable condition. πŸ›€οΈπŸ”§

πŸ’ͺ Precision and Progress: In addition to the aforementioned achievements, we successfully installed Signal hardstands for BEF2336/2338, BEF2349, BEF2381, and BEF2207. Our commitment to precision ensures the rail infrastructure is prepared for future demands. πŸ› οΈπŸ“

Kevin Brindley, Enable Project Manager said: β€œI extend my gratitude to the Enable Infrastructure team and our valued partners at Network Rail for their dedication and collaborative efforts. The successful completion of Feltham Phases 3 & 4 concluding works underscores our shared commitment to enhancing rail infrastructure for the benefit of all stakeholders.” πŸŒŸπŸ—οΈ